I have a new 12 ton geo system installed. The water in was coming in way hot. The contractor who has been wonderful has been to the moon and back trying to find the problem. We found the issue... The well digging company has admitted that they hit a handful of caves and did not use any casing. The well company have decided to re-drill 12 new wells free of cost except for the hard cost of casing. My ? Is. Is there any other option out there than all new wells?
Thanks for any help!!
Phogan