Page 1 of 3 123 LastLast
Results 1 to 13 of 27

Thread: JCI FX Builder

  1. #1
    Join Date
    Jan 2005
    Location
    Miami, Florida
    Posts
    41

    JCI FX Builder

    Hope everyone is enjoying the Holidays!

    I'm an old dog trying to learn a few new tricks. Trying to get away from the physical end of this trade.
    I am learning the FX Builder program and would like to ask the more experienced techs for some help.
    I am trying to develop a chiller plant control strategy and need to work out the pump & chiller staging.
    Does anyone out there have assemblies built for pump lead/lag with auto start on failure? How about sequencing 3 parallel chillers.
    I'm part way through the design and have reached the end of my ability.
    If someone could provide an assembly or two, it would get me headed in the right direction.

    Email address is in my profile.
    Thank you!
    Do the best you are capable of, be totally honest, die with a smile on your face!

  2. #2
    Join Date
    Jan 2005
    Location
    Miami, Florida
    Posts
    41
    Bump
    Do the best you are capable of, be totally honest, die with a smile on your face!

  3. #3
    Join Date
    Dec 2007
    Location
    Connecticut
    Posts
    937
    Hello tlrsr,
    I have some pump lead/lag routines that I have used in the field and work quite well. They switch lead pump base on run hours and also switch on pump failure. I also have an assembly that stages 4 chillers on and performs lead rotation based on run hours or a manual lead select from an operator workstation. I am commissioning the chiller job on Monday and if all goes well I will send you the fine tuned assemblies.

  4. #4
    Join Date
    Jan 2005
    Location
    Miami, Florida
    Posts
    41
    Quote Originally Posted by The Reaper View Post
    Hello tlrsr,
    I have some pump lead/lag routines that I have used in the field and work quite well. They switch lead pump base on run hours and also switch on pump failure. I also have an assembly that stages 4 chillers on and performs lead rotation based on run hours or a manual lead select from an operator workstation. I am commissioning the chiller job on Monday and if all goes well I will send you the fine tuned assemblies.
    That would be fantastic! Thank you.
    Do the best you are capable of, be totally honest, die with a smile on your face!

  5. #5
    Join Date
    Jan 2005
    Location
    Miami, Florida
    Posts
    41
    Reaper! Please resend your application. I received the email on my mobile and didn't download the application. It was supposed to remain on the server, but of course when you count on something, it never materializes.
    Do the best you are capable of, be totally honest, die with a smile on your face!

  6. #6
    Join Date
    Dec 2007
    Location
    Connecticut
    Posts
    937
    Here it comes.

  7. #7
    Join Date
    Jul 2007
    Location
    Southwest Florida
    Posts
    61
    Quote Originally Posted by The Reaper View Post
    Hello tlrsr,
    I have some pump lead/lag routines that I have used in the field and work quite well. They switch lead pump base on run hours and also switch on pump failure. I also have an assembly that stages 4 chillers on and performs lead rotation based on run hours or a manual lead select from an operator workstation. I am commissioning the chiller job on Monday and if all goes well I will send you the fine tuned assemblies.
    Reaper, Please send me the mcr files also.
    I'm working on designing pump rotation assemblies - If I
    can look yours over it would be a great help.

    THANKS!!!

    Email is in my profile.

  8. #8
    Join Date
    May 2007
    Posts
    50
    Quote Originally Posted by ;
    Reaper, Please send me the mcr files also.
    I'm working on designing pump rotation assemblies - If I
    can look yours over it would be a great help.
    I would also be interested to taking a look at your work, my E-mail is also in my profile.

    Many thanks

  9. #9
    Join Date
    Dec 2007
    Location
    Connecticut
    Posts
    937
    Hi Guys
    I sent those assemblies out this afternoon. I didn't know if the pumps had drives or mag starters so I sent both. Good Luck.

  10. #10
    Join Date
    May 2009
    Location
    Vancouver
    Posts
    1
    The Reaper - I would really appreciate if you send me the lead/lag assemblies - my email address is in profile. I am new to FX Builder and currently working on my first project.
    Thanks!!!

  11. #11
    Join Date
    Dec 2007
    Location
    Connecticut
    Posts
    937
    You've got mail.

  12. #12
    Join Date
    Mar 2009
    Location
    Several Miles from Sane
    Posts
    1,472
    Reaper, you are too nice !
    Could I pursuade you to send them to me also?

    Thanks a ton, you "Da Man"

    email in profile.
    If sense were so common everyone would have it !

    All opinions expressed are my own. Any advice provided is based on personal experience, generally accepted fact or publicly available information. As such, it is worth exactly what you paid for it, not a penny more not a penny less !!

  13. #13
    Join Date
    Dec 2007
    Location
    Connecticut
    Posts
    937
    Here they come. Let me know if you don't get them. I've been having email issues lately.

Page 1 of 3 123 LastLast

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  