    Lifting sections of ductwork high in the air???

    The general question is this. What is a good way to lift 20- 25' sheet metal sections of ductwork pre fabbed in the shop and shipped to the field rather than installing small sections by section? The duct must be lifted 20-30 ft in the air. Any help would be appreciated? Thanks.

  2. #2
    Join Date
    Nov 2004
    Location
    Central Oregon
    Posts
    131
    I used to use 2 scissor lifts
    When the going gets weird, the weird turn pro. HST

  3. #3
    Join Date
    Oct 2007
    Location
    Milwaukee,WI
    Posts
    1,066
    We use these a lot to put large sections of TDC ductwork up in the air as it is easier to put the sections together on the ground. On longer sections we use two lifts.

    http://www.toolfetch.com/Brand/Genie...-25.htm?per=25

    I think 25' is as high as they make them though.
    ___________________________

    Chicago is an indian word for stinky!!!!!!
    -supertek65

  4. #4
    Join Date
    Mar 2007
    Posts
    3,057
    There's a couple different methods I've used before, but I always tried to use the duct jack(s) whenever I could.

    Two scissor lifts back to back with 2x4s laid across the top rails

    two chainfalls with rigging straps (if you have room to hook them up to the joists)

    And in extreme cases, a forklift or "Lull", if you know what that is... I'm sorry I don't know it by it's actual name...

  5. #5
    Join Date
    Sep 2002
    Location
    Boise Idaho
    Posts
    1,032
    2 scissor lifts with blocks of wood and either material lifts or high reach forklifts to get it on the scissors (unless you have 6 guys on the job). I usually go with 12'-16' max, anything more you can damage yourself or the duct. For spiral if using couplers sometimes 2 sticks if its a wherhouse and I have a forklift.

    matt

  6. #6
    Join Date
    Mar 2007
    Posts
    3,057
    Quote Originally Posted by Mstrav View Post
    2 scissor lifts with blocks of wood and either material lifts or high reach forklifts to get it on the scissors (unless you have 6 guys on the job). I usually go with 12'-16' max, anything more you can damage yourself or the duct. For spiral if using couplers sometimes 2 sticks if its a wherhouse and I have a forklift.

    matt
    12'-16'?! Ever done shopping mall buildouts? You have to sling 40' at a time just to keep up with the other trades on those jobs!

  7. #7
    Join Date
    May 2004
    Location
    Rapid City, SD
    Posts
    7,403
    We did a fairly big job kinda like that.

    12'-16' is the normal longest I ever went, but for the most part, I was solo.

    One big building we did (there was 5 of us there) was awesome. From the drops it was a straight run out 2 ways, and I think there were like 7 or 8 drops.
    1 guy was the ground monkey, running around helping everyone. One guy ran the lift, one guy putting hangers up and 2 guys in man lifts installing the duct. I dunno how long of chunks we put up, but they were close to 30' I bet.

    I think we spent 2 days putting duct together and getting everything ready, then we started hanging. Man that job went insanely fast, I miss those kinda jobs. Unfortunately I always got stuck on those jobs where you'd spend all day hanging 20' because of all the crap in the way.
    "If you call that hard work, a koala’s life would look heroic."

    VETO PRO PAC, The Official Tool Bag of HVAC-Talk.com

    Testo... you guys rule!

  8. #8
    Join Date
    Jul 2006
    Location
    MN
    Posts
    173
    Try these guys. They may have something to meet your needs.

    http://www.ur.com/index.php/equipmen...l+Lifts&page=1

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
Comfortech Show Promo Image

Related Forums

Plumbing Talks | Contractor Magazine
Forums | Electrical Construction & Maintenance (EC&M) Magazine
Comfortech365 Virtual Event