Question to all,
Is there any reason I would want to delay start up of chillers by 15 or 20 minutes each thru the BAS program? For instance after a power outage the lead chiller will start up after a 20 minute delay. It will immediately want a second unit to start but has to wait 15 more minutes. And keep in mind this is after the first chiller has waited 20 minutes. Meaning it will be over 30 minutes before 2 chillers are on line. Thats a long time. Anybody have any thoughts on this sequencing? Carrier 19xrvs are the units in question.